RoRo dimension limits that cancel bookings

The measurements that most often disqualify a machine from RoRo, and what to do when it happens.

RoRo dimension limits that cancel bookings

RoRo is the most efficient way to move wheeled cargo, and the most unforgiving when the dimensions are wrong. These are the limits we check first.

Height

Deck clearance varies by vessel but commonly sits between 4.2 and 4.6 metres on the main decks, and lower on hoistable decks. A machine that is 4.4 metres tall may fit one vessel and not the next, which is why the answer is vessel-specific rather than trade-specific.

Width

Ramp width is usually the binding constraint, not deck width. Most ramps accept around 4.5 to 6 metres, but stanchions and internal ramps reduce the usable envelope. Wide dozers, graders and pavers need a specific check.

Ground clearance and ramp angle

The break-over angle at the top and bottom of the ramp is where low-hanging components catch. Machines with front attachments, low fuel tanks or long rear overhangs are the usual problem. Photograph the lowest point and tell us the clearance.

Weight and deck loading

Total weight is only half the question. Deck plating is rated per square metre, and a small footprint with a high point load can exceed the rating even when the total is within limits. Tracked equipment with narrow shoes is a common example.

Self-propelled status

If the unit cannot start, steer or brake, it cannot roll. It can still move on a MAFI trailer, but that changes the booking, the price and sometimes the vessel.

When it does not fit

The options, in order of cost: reduce the machine (remove attachments, fold booms, lower cabs where the manufacturer permits), use a MAFI trailer, use a flat rack, or switch to breakbulk. Each one needs to be decided before the vessel closes, not after the unit arrives at the gate.

Need this checked against your cargo?

Send the dimensions and the lane. A planner will come back with options.

Get a quote Talk on WhatsApp
Certified & audited WCA Member FIATA NVOCC Licensed ISO 9001:2015 IATA Cargo Agent Customs AEO