What breakbulk freight actually costs in 2026

A line-by-line breakdown of a breakbulk quotation, including the surcharges that surprise first-time shippers.

What breakbulk freight actually costs in 2026

A breakbulk quotation looks short and then grows. The ocean freight is one line; the cost of getting the piece to the hook, securing it and getting it off at the other end is several more. Understanding the structure is the difference between comparing two quotes fairly and comparing two different scopes.

1. Ocean freight

Quoted per revenue tonne (FRT), which is the greater of cubic metres or metric tonnes. A 40-tonne piece occupying 60 cubic metres bills on 60 FRT. Rates on the China–Middle East trade have ranged roughly USD 45–95 per FRT for multipurpose vessels in the past year, depending on direction, vessel size and how badly the operator needs the cargo.

2. Heavy-lift surcharge

Applied when a single piece exceeds the vessel's crane capacity, or when a tandem lift is required. It is usually a lump sum per piece rather than a per-tonne rate, and it can add 10 to 25 percent to the ocean freight on a project shipment.

3. Lashing and securing

Either included in the carrier's freight or quoted separately by a lashing contractor. For complex pieces — machinery on skids, bundled steel, anything with a high centre of gravity — expect a separate line and a method statement.

4. Port handling

Terminal handling charges at origin and destination, plus stevedoring where the terminal does not include it. These are local charges and are rarely included in the ocean freight. They are also the line most often omitted from a first quotation, which is why the final invoice can look 20 percent higher than the quote.

5. Documentation and surveys

Bill of lading, certificate of origin, export declaration and, where required, pre-shipment inspection. A condition survey at the load port is inexpensive relative to a disputed claim and we recommend it for anything above roughly USD 100,000 in value.

6. Inland legs

Factory to port, and port to site. For out-of-gauge cargo this can exceed the ocean freight, particularly where permits and escorts are needed. The inland leg is also where schedules slip, because it depends on road conditions rather than sailing dates.

What a realistic split looks like

On a recent 68-tonne transformer shipment from Shanghai to Jebel Ali, the ocean freight and heavy-lift surcharge accounted for about 55 percent of the total. Port handling was 14 percent, lashing 9 percent, inland haulage and permits 17 percent, and documentation and surveys 5 percent. Any quotation that shows only the ocean line is telling you less than half the story.

How to compare quotes

Ask each forwarder to confirm, in writing, what is included: lashing, terminal handling at both ends, surveys, permits, and the destination delivery terms. A cheap quote with exclusions is not cheap; it is incomplete.

Need this checked against your cargo?

Send the dimensions and the lane. A planner will come back with options.