Breakbulk vs RoRo: choosing the mode for heavy equipment

RoRo is cheaper until the machine will not fit the ramp. Here is the decision sequence we use before quoting either option.

Breakbulk vs RoRo: choosing the mode for heavy equipment

Every heavy equipment enquiry arrives with the same question underneath it: can this machine roll on, or does it have to be lifted? The answer decides the mode, the price and, often, the sailing date.

The four numbers that decide it

Before we compare rates we check four measurements. They are not negotiable, because they are physical limits of the vessel rather than commercial preferences.

  • Height. RoRo deck clearance typically tops out around 4.2 to 4.6 metres depending on the vessel and the deck. A machine that clears the ramp may still fail a deck.
  • Width. Ramp width and internal stanchion spacing matter more than deck width. Wide dozers and graders are the usual casualties.
  • Ground clearance and ramp angle. Low-hanging components catch the ramp break-over point. This is common with tracked equipment fitted with attachments.
  • Weight per axle or per square metre. RoRo decks are rated; a concentrated load can exceed the deck even when the total weight is acceptable.

When RoRo wins

For standard excavators, wheel loaders, buses and trucks, RoRo is usually 15 to 30 percent cheaper than breakbulk on the same lane, and the cargo is handled less. There is no crane hook, no lifting points to certify, and no lashing plan to approve. The unit rolls on at the load port and rolls off at discharge.

The catch is the calendar. PCTC and RoRo services run on fixed rotations, and a missed cut-off can mean a two-week wait. If the machine is ready on a Monday and the vessel closes on Tuesday, the saving can disappear into storage.

When breakbulk wins

Breakbulk takes over when the machine exceeds a ramp or deck limit, when it cannot move under its own power, or when it is shipped together with out-of-gauge components that have to travel on the same bill of lading. It is also the better answer when the cargo includes a mix of rolling and non-rolling pieces, because the whole shipment can be stowed together.

Breakbulk pricing is usually per revenue tonne — the greater of cubic metres or metric tonnes — plus a heavy-lift surcharge when a single piece exceeds the vessel's crane capacity. That structure means a light but bulky machine can price surprisingly high.

The comparison we send

When the cargo is borderline, we quote both modes with the same assumptions: same origin, same destination, same date window. The comparison includes the inland leg, because a RoRo terminal is often further from the factory than a breakbulk berth, and that difference can close the gap.

Rule of thumb: if the unit fits the ramp and the deck, RoRo is the default. If it does not, breakbulk is not a fallback — it is the only option, and the planning starts earlier.

What to send us

Photos of all four sides, the model and serial number, operating weight, transport dimensions (not brochure dimensions), ground clearance and whether the unit starts and steers. With those, we can usually confirm the mode within a working day.

Need this checked against your cargo?

Send the dimensions and the lane. A planner will come back with options.