The China–Africa trade carries some of the widest gap between quoted and realised transit times. The causes differ by coast, and so does the remedy. Here is the 2026 pattern lane by lane.
West Africa: Lagos, Tema, Abidjan
Marine transit from Chinese ports runs 30 to 38 days. The variable is Lagos: berth congestion and customs examinations add 3 to 10 days routinely, more in peak quarters. Tema performs steadier; cargo that can clear through Ghana moves faster even with an extra inland leg. Pre-declaration and correct HS documentation are the whole game on this coast — a single certificate mismatch can add a week inside the terminal.
East Africa: Mombasa, Dar es Salaam
Transit of 28 to 35 days with moderate berth risk. The real constraint is inland: cargo to Uganda, Rwanda and the DRC enters bonded corridors where the next border is the schedule risk. Book the corridor leg with the ocean leg; separate bookings at Mombasa produce exactly the yard waits the corridor was designed to avoid.
Southern Africa: Durban and beyond
Durban is the best-performing African hub for schedule reliability, 24 to 30 days marine transit. Breakbulk and project cargo discharge here with decent heavy-lift availability, which makes Durban the practical entry for Southern African project loads despite longer inland legs.
Buffers that belong in the plan
Plan 4 to 7 days beyond marine transit on West African lanes, 3 to 5 on East African, and 2 to 3 via Durban. The buffer is not padding — it is what the receiver plans against, and an honest range beats a confident date that misses.
Frequency and the missed-sailing cost
Sailings are weekly to major ports, fortnightly to secondary ones. A missed cut-off on a fortnightly service is a two-week slip. Cut-off discipline and pre-booked documentation review are the cheapest transit improvements available on this trade.