Tools Support
Get a quote Talk on WhatsApp
Guide

Tandem lifts and heavy-lift planning: what happens when one crane is not enough

When the piece exceeds the vessel crane capacity, the lift becomes an engineering exercise. Here is what that means for your schedule and your budget.

Tandem lifts and heavy-lift planning: what happens when one crane is not enough

A 41-tonne transformer under a 42-tonne crane is a lift. A 68-tonne transformer under two 42-tonne cranes is a tandem lift — a different engineering exercise with different failure modes, and it needs to be planned as one at the quotation stage.

When tandem lifts enter the picture

Vessel cranes on multipurpose ships range from 30 to 120 tonnes. Above a single crane rating, two cranes lift the piece together through a spreader system. Tandem lifts are routine on experienced vessels but they require certified lift plans, load-tested spreaders and, usually, a specialist lashing contractor on hand.

What the lift plan contains

Centre of gravity marked on the piece, sling angles with their resulting loads, crane positioning and slew limits, ground bearing pressure at the quayside, and the sequence of the lift itself. The surveyor signs it before the piece travels to the quay. A missing CoG drawing is the most common reason a lift plan bounces back — and the reason the vessel slips a tide.

What it costs, honestly

Tandem lift premiums are typically a lump sum per piece — roughly 1,500 to 4,000 dollars depending on the trade and the gear — plus the spreader rental and the survey. On a project shipment this can add 10 to 25 percent to the ocean freight. It is not a number to discover at loading; it is a line item to negotiate at quotation.

Alternatives worth pricing

Sometimes a floating crane at the discharge port beats a tandem lift at sea. Sometimes the piece travels disassembled and the tandem lift becomes two ordinary lifts. Both alternatives change the schedule — the floating crane option needs a weather window, the disassembly option needs factory time. We price all three when the piece is borderline, with the schedule consequences written next to each number.

What you should send

Weight, CoG drawing, lifting points certified for the load, and photographs. If lifting points are uncertified, say so — we price engineered lifting frames instead of discovering the problem under the crane.

Need this checked against your cargo?

Send the dimensions and the lane. A planner will come back with options.

Get a quote Talk on WhatsApp
Certified & audited WCA Member FIATA NVOCC Licensed ISO 9001:2015 IATA Cargo Agent Customs AEO