A vessel schedule looks like two dates — departure and arrival. It is actually five or six, and the unquoted ones decide whether your cargo is on the vessel. Here is the full anatomy.
ETD and ETA: the headline numbers
Estimated time of departure and arrival frame the transit. They are estimates: ETD moves with port congestion upstream, ETA moves with weather and rotation order. Quote the range, not the number, when receivers plan labour against arrival.
Cut-off: the deadline that is not the departure
Documentation cut-off and cargo cut-off are separate, and both precede the ETD — often by 24 to 48 hours on container services. Cargo cut-off for breakbulk is frequently earlier still, because stow planning must be final before the stow meeting. Missing documentation cut-off while making cargo cut-off is a classic; the cargo sails without a bill of lading and the delay lands at destination customs instead.
Berthing window and tide
At secondary ports, vessels work within berthing windows and tidal constraints. A vessel that misses its window can wait a tide — or a day — before it berths. This is why the same voyage can arrive on schedule at one port and slip at the next.
Free time starts at discharge
The arrival date starts the demurrage and storage clocks. Receivers who plan to the ETA without the buffer meet the clocks sooner than expected. Free time is contractable — ask what applies at the destination port before booking, not after the container is in the yard.