Most project cargo delays are not caused by the vessel. They are caused by information that arrived too late to act on. This checklist is the one we run before confirming a booking.
Cargo information
- Transport dimensions, not catalogue dimensions. Include packaging, skids, protruding flanges and any temporary bracing.
- Weight per piece, and centre of gravity. The crane operator needs the CoG to rig the lift safely.
- Lifting points and their certification. If the piece has no certified points, a lifting study is required before quotation.
- Photos or drawings. A single drawing replaces several email threads.
Route information
- Origin address and access. Gate width, overhead lines, yard surface and crane access at the factory.
- Destination address and access. The last kilometre is where most out-of-gauge cargo fails.
- Permits required. Abnormal load, road closure, police escort, port access.
- Bridge and overhead line clearances. A route survey is cheaper than a recovery.
Commercial information
- Cargo value and insurance basis. Cover has to match the handling method.
- Incoterms. Who arranges the inland leg, the insurance and the destination clearance.
- Required delivery date, and the consequence of missing it. This determines how much buffer to buy.
- Documentation requirements at destination. Import permits and standards marks can take longer than the sailing.
What happens next
With those twelve items, we can usually produce two or three viable plans within three working days, each with a cost, a transit time and a stated risk. Without them, the only honest answer is a range so wide it is not useful.
Send the dimensions and the lane. A planner will come back with options.