Project cargo insurance is cheaper to buy well than to claim badly. Premiums on out-of-gauge machinery run from 0.15 to 0.6 percent of value depending on the risk story — and the story is constructed from engineering documents, not adjectives.
Institute Cargo Clauses: the base choice
ICC (A) covers all risks of physical loss or damage; ICC (B) and (C) list named perils only. Machinery moving under its own lifting points with a documented lift plan justifies (A) comfortably. The clause choice matters less than the exclusions attached — improper packing, inherent vice and delay exclusions are where claims quietly die.
What the underwriter actually reads
Lift plan with centre of gravity, lashing plan, packing specification, transport route with road legs, and survey reports. A shipment with a pre-stow survey and a certified lift plan prices measurably better than the same cargo without — because the claims history of surveyed cargo is genuinely better. The documents exist for engineering reasons already; sending them to the underwriter costs nothing.
The deduction clauses
Deductibles are per event and per conveyance. Multi-piece shipments arriving across several trucks may accrue several deductibles from one incident. Pair deductibles intelligently, and align them with the real exposure — a 2 percent deductible on a 2-million-dollar transformer is a serious number to plan for.
Delay and consequential loss
Standard cargo policies exclude delay — the machine arrives damaged, repaired, late, and the standby crane you hired is uninsured. Delay cover is available and priced separately. On projects with rental dependencies, price it before deciding it is expensive.
A claim-ready shipment
Photograph at every handover, keep the survey reports, note exceptions on the delivery receipt before signing. Claims are decided on evidence continuity; the evidence costs minutes at each handover and decides payouts measured in weeks.