670-Tonne Girder Deliveries: Breakbulk and Haulage

A 670-tonne girder shipment needs engineered breakbulk loading, port planning and permitted inland haulage. Learn the key costs, documents and timelines early.

670-Tonne Girder Deliveries: Breakbulk and Haulage

A 670-tonne girder delivery requires a coordinated heavy-lift shipping and inland transport plan, backed by verified cargo data, suitable port equipment, engineered lifting and securing arrangements, and an approved route to the final site. For buyers moving large infrastructure components from China to the Middle East, Africa or South Asia, the shipping decision should be made alongside the road-haulage study—not after the girder reaches port.

Why a 670-tonne girder needs project-cargo planning

At this weight, a girder is not routine breakbulk cargo. Its length, width, height, centre of gravity and lifting points can matter as much as its gross weight. A vessel may have sufficient deadweight but still lack the crane capacity, lifting configuration, deck strength or cargo space needed for the specific piece. Similarly, a road transporter may be rated for the weight but unable to negotiate a bridge, tight turn or weak approach road.

Start by treating the shipment as one connected chain: factory collection, export port, ocean transport, discharge port, customs clearance and final delivery. Each handover creates constraints. A late change to the girder’s dimensions or delivery location can affect the vessel, lifting plan, port selection, permits and transport equipment.

Choose a vessel and loading method around the cargo

Compare heavy-lift breakbulk and RoRo options

For a single 670-tonne piece, a geared heavy-lift vessel or a specialist project-cargo vessel is often the first option to assess. The operator must confirm crane capacity for the actual lift radius and tandem-lift arrangement, not just quote a headline maximum lifting capacity. The lift plan also needs to account for the cargo’s centre of gravity, rigging weight, clearance and any operational safety factors required by the vessel and port.

RoRo may be suitable when the girder can be carried on a purpose-built trailer or transporter that can safely roll on and off the vessel. However, ramp capacity, deck loading, turning space and the combined weight of cargo and equipment must all be checked. A berth with a suitable crane may be preferable if the RoRo ramp or vessel deck cannot accommodate the load. Depending on the port and ship, loading may also require a floating crane or a specialist lift arrangement.

Ask the forwarder to evaluate both the loading and discharge ports. A port’s published crane capacity does not automatically mean it can perform this particular lift: outreach, berth depth, quay strength, lifting windows and access for the inland transporter all matter.

Plan port handling before the vessel is booked

Provide the origin and destination terminals with a cargo drawing and handling brief early. The port should review the berth, crane or ramp capability, quay bearing capacity, laydown area, access roads and the method for transferring the girder to its road transporter. If temporary storage is needed, confirm that the terminal can safely support the cargo and keep the area available for the expected period.

Allow time for engineering reviews, terminal approvals and coordination between the ship, stevedore and haulage contractor. Port handling may involve a pre-arrival meeting, lift-plan approval, equipment checks and a defined sequence for lashing removal and discharge. Include contingency planning for weather, equipment breakdown, berth congestion and a missed sailing or discharge window.

Build inland haulage around route limits

A 670-tonne girder will generally need a specialist heavy-haul solution, which may include self-propelled modular transporters (SPMTs), a modular trailer combination or another engineered configuration selected by the carrier. The final choice depends on the cargo dimensions, axle-load distribution, road geometry, gradients and local regulations. Equipment selection should follow a route study rather than a weight estimate alone.

Survey the complete route

A route survey should check bridges and culverts, pavement strength, overhead clearances, turning radii, road width, gradients, roundabouts, utility lines and access to the project site. It should also assess whether traffic management, temporary road works, bridge strengthening or utility lifting is required. At the destination, confirm the unloading area’s ground-bearing capacity and the space needed to position the transporter and lifting equipment.

Obtain permits and police or road-authority escorts where required, and confirm permitted travel windows. In some locations, the route may need to be cleared or modified before cargo arrives. A practical delivery plan includes the sequence of approvals, enabling works and site readiness checks, with named responsibility for each item.

Understand the main cost and schedule drivers

There is no reliable flat freight rate for a 670-tonne girder. A project quotation depends on the cargo’s dimensions and lifting points, vessel availability, route and port pair, equipment needs, handling method, season, fuel and vessel-market conditions, and whether the shipment can move with other compatible project cargo. Inland costs vary with distance, road permits, escorts, route modifications, transporter configuration and site access.

Request a cost breakdown that identifies ocean freight, origin and destination handling, heavy-lift or crane charges, lashing and securing, documentation, inland haulage, permits, surveys, storage and any quoted exclusions. Clarify how standby, demurrage, weather delay and changes to the cargo specification would be charged. Comparing offers only by the ocean-freight line can hide significant costs at the ports or on the final road leg.

As a planning guide, ocean transit from China to the Middle East, South Asia or parts of Africa can commonly take around two to five weeks port-to-port, depending on the specific ports, direct or transshipment routing, vessel schedule and congestion. This is not a delivery promise. Engineering, port approvals, export readiness, customs, inland permits and site preparation may add several weeks to the overall project timeline. Build schedule margin around approvals and vessel cut-offs, and confirm the current sailing plan before committing installation dates.

Prepare the cargo documents and technical data

Send the forwarder complete cargo particulars as early as possible: confirmed gross weight, overall dimensions, lifting points, centre of gravity, support points, drawings, material and packing details, and any restrictions on orientation or handling. If the girder is being shipped with accessories, identify each piece and its weight separately. The cargo data should match the final production and packing information.

Typical documents include the commercial invoice, packing list, export declaration and bill of lading instructions. The shipper may also need certificates of origin, permits or other documents required by the destination country. For oversized road transport, provide the technical drawings and information required by local permit authorities. The shipping and haulage teams should confirm who prepares each document and the deadline for submission.

Agree the lift plan, method statement, stowage and lashing plan, and any required engineering approvals before cargo acceptance. Keep copies of approved drawings, equipment certificates and inspection records with the project file. Destination customs requirements differ, so verify the applicable paperwork with the importer or customs broker rather than relying on a generic document list.

Protect the girder and insure the full movement

Use transport supports and cradles designed for the girder’s weight and shape. They should distribute loads without damaging structural members, coatings or machined surfaces. Protect vulnerable ends and connection points, and use suitable coverings where exposure to salt spray, moisture or dust could cause damage. Mark the centre of gravity and approved lifting points clearly, and ensure markings remain visible after loading.

Insurance should reflect the value and risk of the complete movement, including lifting, port storage, ocean transit, discharge and inland haulage. Check whether the policy covers loading and unloading, temporary storage, delay-related exclusions and damage during road transport. Confirm that declared values, packing descriptions and transport stages are accurate, and ask the insurer or broker about any survey or notification requirements before work begins.

FAQ

Can a standard container ship carry a 670-tonne girder?

Usually not as a conventional container load. A suitable heavy-lift or project-cargo vessel should be assessed against the piece’s weight, dimensions and handling requirements.

How long does delivery take?

Ocean transit may take about two to five weeks, but approvals, port handling and inland permits can extend the end-to-end schedule.

What information is needed for a quote?

Provide dimensions, weight, drawings, lifting points, origin and destination, delivery location, cargo-ready date and any known route constraints.

Need this checked against your cargo?

Send the dimensions and the lane. A planner will come back with options.

Get a quote Talk on WhatsApp
Certified & audited WCA Member FIATA NVOCC Licensed ISO 9001:2015 IATA Cargo Agent Customs AEO